Basic Emergency Response Plan of Action |
 |
 |
Note: The following was developed for a specific large fire loss involving roof damage. Actions may not pertain to your loss or other actions may be required but this list can be a starting point.
Information - Time Sensitive Decisions
Full set of blueprints
Names of service contractors
Request information from tenants:
Hazardous materials
HAZCOMM - MSDS
Security issues
Contents Safety
Physical Hazards
Bring in a structural engineer
Shoring
Remove broken glass
Remove exterior debris
Remove materials that are dangerous
Fall protection
Evacuation plan
First aid station(s)
Identify and remove hazardous materials
Security
Temporary Fence
Guard service
ID Badges - log in and log out
Control access - ingress and egress
Emergency Services
Pump out basement
Extract water from floors
Debris removal - safety
Temporary Restore Services
Check on demolition permits
Generator - 60 kw
Temporary lighting
Sanitary facilities
Hand wash station
Debris chutes
Shrink wrap roof
Temporary heat
Contact electrician
Contact elevator company
Contact gas company
Contact HVAC contractor
Contact plumber
Contact fire suppression company
Phase I
Stabilize building interior environment through emergency mitigation and structural drying incorporating desiccant dehumidification.
- Meet with adjuster and all parties for briefing
- Mobilization of drying equipment, generators, crane
- Notification of temporary labor supplier
- Notification of Engineer
- Notification of subcontractors
- Contact appropriate local government officials for permits, etc.
- Install security fencing, control access- ingress and egress
- Deploy on-site command center
- Establish site communication system
- Retain lodging for support staff
- Establish basic safety program
- Mobilize disposal services
- Mobilize sanitary services
- Receive drying equipment, generators, and crane
- Inspect roof damage
- Receive materials at site for emergency mitigation
- Receive and review building plans
- Confirm all prior notifications and appointments
- Bring all staff and techs on project plans, team plans
- Bring all personnel on site
- Meet with Fire Marshall to receive control of building
- Meet with all parties for walk through
- Safety officer and team complete site specific safety plan
- Install temp lighting
- Construct temp roof system over fire breaches
- Commence pumping out basement
- Deploy initial dehumidification
- Commence extraction
- Commence content removal procedures
- Commence demolition of unsalvageable building materials
- Continue towards completion all phase I activities
- Expect to tie in electric by day 5
- Maintain drying, monitoring and management of moisture removal
|
|